Pet and Household Care Manufacturer
A leading pet and household care manufacturer located in the East of England
The Client
Contracted Specialist Coatings to refurbish and line an eight-year-old hot well tank that supplied the factory with hot water.
Hot well located above an industrial boiler, not the only problem.
Challenges
- This leaking tank had multiple areas of sever corrosions, deep pitting and craters which reassembled the surface of the moon.
- Due to its high temperature, the water seeping from the tank was potentially hazardous.
- It was located, approximately 3m above a boiler, which was to say the least has difficult access.
- The factor was still in operation ,the boiler was operational throughout the project, the entrance temperature reached 40°C.
- Numerous hot pipes were located near the manway entrance.
- A complex array of internal steelwork made working conditions difficult.
- An external plate at been welded to the underside of the tank in an attempt to stem the leaks.
- Due to the tight positioning of the tank, replacing it would be costly and time-consuming.
- Not an easy project, however we thrive on difficult project most other companies would run from.
Before Treatment
Solution
To repair and refurbish this hazardous and failing tank, we applied a special high-temperature tolerant epoxy tank lining system, suitable for use in confined spaces. The specialist low odour, solvent-free glass flake reinforced system was potable water and food contact approved.
The internal surfaces of the tank were extensively blast cleaned with abrasive grit to SA2.5 to remove rust, dust, scale and other deposits. Having cleaned the tank, a primer coat of high-temperature-resistant resin was applied and a total of seventeen holes and deep craters that were close to perforation were filled using a special resin-based surface repair system.
The floor of the tank was reinforced with a screed coating. A high temperature-resistant main coat was applied in multiple layers to ensure complete coverage. We rigorously tested the tank linings throughout each process for coating thickness and the absence of holes in the new lining.
After Treatment
The Results
By restoring the tank lining, we were able to bring the tank back into optimum production and extend its lifespan by ten to fifteen years, subject to regular inspections and general maintenance.
The project was completed on time as projected and the onsite engineer confirmed the expense of lining the existing tank cost 10% of the price of full tank replacement.
Most of all a happy client.